Eggenbach power plant, Austria
At Eggenbach power plant, it became necessary to buy new machines after just two years due to problems and slow performance. The decision was made to opt for a Pelton turbine and a machine unit from AEM. This allowed performance to be doubled to between 2.5 and 3 GWh per year.
Type | SE 500 M10 |
---|
Number of units | 1 |
---|
Machine type | generator / synchronous |
---|
Degree of protection | IP 21 |
---|
Cooling system | IC 01 |
---|
Rated speed [rpm] | 600 |
---|
Rated power [kVA] | 600 |
---|
Rated voltage [V] | 400 |
---|
Rated frequency [Hz] | 50 |
---|
Shaft height [mm] | 500 |
---|
Mounting | IM B3 |
---|