Furkelbach power plant, Italy

In the ski region of South Tyrol, acceptable solutions had to be found for two sites, as water from the Furkelbach is used by cablecar operator Olanger Seilbahnen AG for snow-making systems. An agreement was reached thanks to a 50 l/s pump back. The operating company is 80% from the town of Olang and 20% private. Thanks to the combination of Pelton turbines and an AEM synchronous generator, it is possible to feed over 2 GWh into the local network for this purpose each year. The payback period for the site is around 8 to 10 years.

Technical data

Type SE 450 S6
Number of units1
Machine type generator / synchronous
Degree of protection IP 44
Cooling system IC 81W
Rated speed [rpm] 1.000
Rated power [kVA] 650
Rated voltage [V] 400
Rated frequency [Hz] 50
Shaft height [mm] 450
MountingIM V1

Contacto rápido

Tel.: +49 340 203-200
Fax: +49 340 203-311
Correo electrónico:
info@aemdessau.de
Formulario de solicitud
Persona de contacto